The Mint Town Center at Stapleton
As Site Foreman, managed the entire project from start to finish. During the Finish Phase, promoted to Plumbing Superintendent for multiple jobsites and guided a new Site Foreman to TCO. Coordinated every plumbing system across residential, commercial, and common areas.
Project Details
Location
East 29th Avenue Town Center, Stapleton (now Central Park), Denver, CO
Timeline
2016 - 2018
General Contractor
CFC Construction, Inc.
Employer
Freund Plumbing and Heating
Construction Type
Mixed-use luxury development with parking garage
Technical Details
- 399 units with 37 different floor plan configurations (575 SF to 1,600+ SF)
- LEED Silver certified - all LED lighting throughout
- Mixed-use: residential units + ground-floor retail/restaurant
- Olympic-sized swimming pool plumbing
- Complete storm drainage system, 2 grease traps, 1 sand/oil interceptor
- Largest single building in Stapleton development at time of construction
- Engineered DWV system PRO-VENT (similar to cast iron solvent)
Role: Site Foreman to Plumbing Superintendent
All Underground Layout, All Rough Layout, Material/Takeoff, Project Management and Meetings, Management of all Plumbing Foreman and Personnel onsite. GC Meetings, MEP coordination, Submittal Revisement, Change Orders.
Completed Scope
Underground, Rough, and Final Layout. All Underground and Rough Inspections. Final Plumbing Decision Maker throughout the entire project. Promoted to Plumbing Superintendent.
Project Gallery69 photos from the jobsite













.jpg&w=3840&q=75&dpl=dpl_CLKuYiQLuaMwmSjBydL4Khi8NVgy)






.jpg&w=3840&q=75&dpl=dpl_CLKuYiQLuaMwmSjBydL4Khi8NVgy)













.jpg&w=3840&q=75&dpl=dpl_CLKuYiQLuaMwmSjBydL4Khi8NVgy)






.jpg&w=3840&q=75&dpl=dpl_CLKuYiQLuaMwmSjBydL4Khi8NVgy)



















.jpg&w=3840&q=75&dpl=dpl_CLKuYiQLuaMwmSjBydL4Khi8NVgy)